Thank you for visiting A project has the following risks 20 probability of a 14 day delay in the receipt of customer requirements 10 probability of a 21 day. This page is designed to guide you through key points and clear explanations related to the topic at hand. We aim to make your learning experience smooth, insightful, and informative. Dive in and discover the answers you're looking for!

A project has the following risks:

- 20% probability of a 14-day delay in the receipt of customer requirements.
- 10% probability of a 21-day delay.

What is the expected value of these events?

A. 49 days
B. 8 days
C. 11.9 days
D. 35.9 days

Answer :

Final answer:

The expected value of the project delays is 4.9 days, calculated by multiplying each delay duration by its probability and summing the results.

Explanation:

The question provided asks for the expected value of project delays given certain probabilities and durations of those delays. To calculate the expected value of these risks, we multiply each delay by its corresponding probability, and then sum the results.

The first risk is a 20 percent probability (0.20) of a 14-day delay, and the second risk is a 10 percent probability (0.10) of a 21-day delay. Following the formula for expected value, we would calculate:

  • (0.20 * 14 days) + (0.10 * 21 days)
  • (2.8 days) + (2.1 days)
  • 4.9 days

Hence, the expected value of the delays is 4.9 days. This means that on average, the project can be expected to be delayed by about 4.9 days due to these risks. This is a project management calculation widely used in risk analysis and planning.

Thank you for reading the article A project has the following risks 20 probability of a 14 day delay in the receipt of customer requirements 10 probability of a 21 day. We hope the information provided is useful and helps you understand this topic better. Feel free to explore more helpful content on our website!